Installation 3
3.4 SCL/SCM Power Wiring Diagram
4.5 lb-in / 0.5 Nm
0.24 in / 6 mm
10 lb-in / 1.2 Nm
0.35 in / 9 mm
18 lb-in / 2.0 Nm
0.5 in / 13 mm
15 HP
(11 kW)
7.5 - 10 HP
(5.5 - 7.5 kW)
0.25 - 5 HP
(0.37 - 4 kW)
L1
L1
L1
Single Phase Models
Three Phase Models
208/240V up to 5Hp
400/480V up to 7.5Hp
Three Phase Models
208/240V 7.5Hp and larger
400/480V 10Hp and larger
Output
Output
L2/N
PE
B- B+
Input AC Voltage
Input AC Voltage
PE lug on heatsin
PE lug on heatsink
L2
L3
B-
B+
L2
L3
UVWPEPE
PES
PES
PES
3-Phase
AC Motor
3-Phase
AC Motor
T1 T2
T3 B-
B+
+
-
DC
Bus
Torque Requirements
WARNING!
• DO NOT connect incoming AC power to output terminals U, V, W, or terminals B+,
B-! Severe damage to the drive will result.
• Leakage current may exceed 3.5 mA AC. Minimum size of the protective earth
(PE) conductor shall comply with local safety regulations for high leakage current
equipment.
NOTE
• WIRE AND GROUND IN ACCORDANCE WITH NEC OR CEC, AND ALL APPLICABLE
LOCAL CODES.
• Motor wires MUST be run in a separate steel conduit away from control wiring and
incoming AC power wiring.
• Do not install contactors between the drive and the motor without consulting Lenze
Americas for more information. Failure to do so may result in drive damage.
• Use only UL and CSA listed and approved wire.
• Minimum wire voltage rating is 300 V for 120, 208, and 240 Vac systems, and 600
V for 400 and 480 Vac systems.
• Wire gauge must be based on a minimum of 125% of the rated input/output current
of the drive, and a minimum 75°C insulation rating. Use copper wire only.