Commissioning
5-1
L BA2141 EN 1.0
5 Commissioning
5.1 First switch-on
Please do not change the switch-on sequence explained below!
Stop!
Prior to first switch-on of the controller, check the wiring for
• Completeness
• Short circuit
• Earth fault
Step Procedure Remarks
1. Connect the basic unit and
if available external supply for the fieldbus
module.
• Onle of the two operating status LEDs at the controller, see ^ 4-1, must be on
or blinking.
If this is not the case, see
^ 7-1
• The green Vcc display must also be on, see ^ 4-1.
If this is not the case, see
^ 7-1.
2. Configuration of controllers connected to
the bus
Configure the controllers connected to the bus by means of an appropriate
configuration tool
à e.g. LONMAKERtfor Windows
®
,see^ 8-1
3. It should now be possible to communicate
with the drive.
The yellow bus LED is blinking, see ^ 4-1, when data is exchanged between
the 2141 fieldbus module and other controllers connected to the bus.
4. Drive-specific settings à Operating Instructions of the basic unit
5. Enable controller à Terminal controller inhibit (CINH) = HIGH
6. Setpoint selection à The drive should be running now.